Proactive’s Tylah Tully breaks down ‘Just the Facts’ of the latest news from Cadoux Ltd.
The company has provided its December 2024 quarterly update, detailing progress on its two critical minerals projects.
Cadoux continued engineering studies for its High Purity Alumina (HPA) project in Western Australia and advanced feasibility studies for the Minhub mineral separation plant in Darwin.
At the HPA project, Stage 1/Phase 2 engineering activities progressed, including Front-End Engineering and Design (FEED) work, equipment fabrication, and environmental planning for the Kwinana production facility.
Marketing efforts continued, with prospective customers assessing HPA samples for heavy-duty electric vehicle applications. Research and development partnerships remain active, focusing on downstream product applications.
Cadoux holds a 50% interest in Minhub Operations Pty Ltd (MOPL) and is fully funding the Minhub feasibility study and associated research.
The study is nearing completion, incorporating engineering improvements.
Minhub aims to process 500,000 tonnes per annum of heavy mineral concentrate from third-party sources, with ongoing discussions …