Here’s a look at the process, by the numbers, according to info from the team’s Corporate and Stadium Communications office.
ORCHARD PARK, N.Y. — Construction of the new Buffalo Bills stadium is underway, and while it won’t be done for another two years, there are some ways to chart the progress made in Orchard Park.
Work on fireproofing, masonry, overhead MEP infrastructure, and metal stud framing are all now underway.
Here’s a look at the process, by the numbers, according to information from the team’s Corporate and Stadium Communications office.
- 313 — That’s the estimated miles of conduit that will be installed.
- 710 — That’s how many workers were on site last week.
- 1,260 — That’s the estimated miles of wire/cable that will be installed.
- 13,421 — That’s how many pieces of steel have been installed.
- 15,952 — That’s how many tons of steel have been installed.
- 23,514 — That’s how many pieces of steel that will eventually be installed.
- …